Kwinana Project Update

Today Adbri announced to the market that we have concluded the detailed review on the Kwinana Upgrade project (KWUP). The KWUP is the largest investment Adbri has made in recent times and is now estimated to cost between $385 million – $420 million, including allowances and contingency. The project remains on track for target commissioning in Q2 2024, with the new plant expected to be fully operational in Q3 2024.  More information is available here